Arthabaska Sainte-Séraphine, Sainte-Élizabeth-de-Warwick et Victoriaville

Since 2022, the Arthabaska wind turbine project has taken shape in the Centre-du-Québec region, very close to Boralex's Kinsey Falls offices. It will be developed in the municipalities of Sainte-Séraphine and Sainte-Élizabeth-de-Warwick, as well as in the City of Victoriaville. This project was selected in January 2024 by Hydro-Québec as part of its call for tenders to secure 1,500 megawatts (MW) of wind power. With 36 to 42 wind turbines and an installed capacity of 265.2 megawatts, the Arthabaska wind farm will be operational from December 1, 2029, supporting Quebec's energy transition.

Project in development

Location

Sainte-Séraphine, Sainte-Élizabeth-de-Warwick et Victoriaville, Quebec, Canada

Description

  • Commissioning dateDecember 2029
  • Contract duration30 years
  • Installed capacity265,2 MW
  • 265 MW Production

  • Between 36 and 42 Wind turbines

Techniciens et techniciennes face à une éolienne

Technical data

  • TurbinesBetween 36 and 42

About Boralex

All you need to know about Boralex's activity worldwide.

This way

Technicien souriant

Project overview

Since 2022, the Arthabaska wind turbine project has taken shape in the Centre-du-Québec region, very close to Boralex's Kinsey Falls offices. It will be developed in the municipalities of Sainte-Séraphine and Sainte-Élizabeth-de-Warwick, as well as in the City of Victoriaville. This project was selected in January 2024 by Hydro-Québec as part of its call for tenders to secure 1,500 megawatts (MW) of wind power. With 36 to 42 wind turbines and an installed capacity of 265.2 megawatts, the Arthabaska wind farm will be operational from December 1, 2029, supporting Quebec's energy transition.The electrical substation will be built in Saint-Albert.

Project development

  • The impact study was submitted in June 2025 https://www.ree.environnement.gouv.qc.ca/projet.asp?no_dossier=3211-12-262
  • A BAPE hearing will be held in spring 2026, and ministerial authorizations would follow in early 2027.
  • Consultation and communications with the community will continue throughout the project.
  • If the project moves forward, construction is expected to begin in fall 2027, with the park becoming operational by the end of 2029.
Configuration parc éolien arthabaska

The project partners

  • MRC Arthabaska : 50 % of parts
  • Boralex : 50 % of parts

Wind power, a key asset for Québec's low-carbon future

With demand for electricity set to rise, Hydro-Québec's Action Plan 2035 - Towards a low-carbon, prosperous Québec, calls for greater use of renewable energies to rapidly meet future energy needs. Wind power is emerging as a competitive solution. With its low production costs, zero GHG emissions and complementarity with hydroelectricity, it is becoming a key lever in Quebec's energy transition.

 

Preliminary timeline

Timeline du projet éolien Arthabaska